PROJECT UPDATES

PW Street Construction

August 2, 2019

Citizens will begin seeing work for the Prince WilliamStreet project that resembles the final roadway this month.  Underground utility work is close to completion, water service connections tothe new underground water main will begin next week.  Once all waterconnections are off of the temporary waterline, the aboveground yellow pipewill be removed. There is still a small portion of sanitary sewer andstorm sewer work that are outstanding, work is progressing to complete theseutility phases of the project.  The contractor is scheduled to begin curband gutter work mid-month.  As it currently stands, the contractor for thePrince William Street project has been granted a contractual extension untilAugust 27, 2019; the latest schedule update from the contractor has indicatedthat the project will be completed in October.  

June 7, 2019

Prince William Street between Wellington Road and Jefferson Street will be closed to through traffic on Saturday, June 8 between 9 AM – 5PM. This section of road will also be closed to traffic between 8 AM – 5 PM Monday – Friday for utility and roadway work; local residences and businesses will still have access to their properties within the work zone.

The contracted 365 days for project completion is almost here; there is still a lot of work to be completed and the contractor has indicated that this contracted date will not be met. The latest schedule from the contractor shows project completion at the end of September. However, based on past performance the City cannot offer assurance that this date will be met. The City will update the public about any schedule changes from the contractor. The City is working with the contractor to accelerate their schedule by allowing some Saturday work, and allowing for flagging operations on sections of Prince William Street outside of the main work zone. Our goal is to deliver the project safely and as quickly as possible, thank you to all of the residents for your continued patience.

May 3, 2019

The intersection of Prince William Street and Wellington Road will be closed from 8 PM Friday, May 3 through 7 AM Saturday, May 4 for underground utility work. 

The work zone along Prince William Street between Wellington Road and Jefferson Street will resume on Monday, May 6. This section of road will be closed to traffic between 8 AM – 5PM Monday – Friday for utility and roadway work; local residences and businesses will still have access to their properties within the work zone.

March 22, 2019

A right turn lane is being added to the Prince William Street project at Wellington Road based on citizen and City Council feedback. This change is achieved by eliminating the dedicated bike lanes for approximately 150 feet at the Wellington Road end of the project; bikes will be accommodated with sharrow markings on the roadway. This solution is accomplished within existing right-of-way and does not impact the construction schedule of the project.

March 1, 2019

Beginning on Monday, March 4 Prince William Street will be closed to traffic from Jefferson Street to Wellington Road between 8 AM – 5PM Monday – Friday for utility and roadway work. Local residences and businesses will still have access to their properties within the work zone. Local access will be from Jefferson Street, no traffic will be able to access Prince William Street from Wellington Road.

February 8, 2019

Letter to residents

January 28, 2019

The stop work order has been lifted and work has resumed.  Travelers should expect delays when traveling along Prince William Street.

January 9, 2019

The City issued the contractor a stop work order based on continual safety and project performance concerns on the project. In their preliminary response, the contractor has committed to the City that they will remedy these issues quickly and work will resume in a timely and safe manner.

December 10, 2018:

Prince William Street will be closed to traffic from Jefferson Street to Wellington Road between 8 AM – 5PM Monday – Friday for utility and roadway work. Local residences and businesses will still have access to their properties within the work zone.

November 16, 2018:

Prince William Street will be closed to traffic from Jefferson Street to Wellington Road between 8 AM – 5PM Monday – Friday for utility and roadway work. Local residences and businesses will still have access to their properties within the work zone.

Wellington Road at Prince William Street will have daily lane closures Monday, Nov. 19 through Wednesday, Nov. 21. Through traffic will be able to travel along Wellington Road, but turns may be restricted.

November 2, 2018:

Prince William Street will be closed to through traffic from Grant Avenue to Wellington Road between 8 AM – 5PM Monday – Friday for utility and roadway work.

Wellington Road at Prince William Street will have daily lane closures Monday, November 5th, Wednesday, November 7, Thursday, November 8 and Friday, November 9. Through traffic will be able to travel along Wellington Road, but turns may be restricted.

The above ground temporary water line (yellow pipe) will be removed next week.

October 29, 2018: 

Prince William Street will be closed to through traffic from Grant Avenue to Wellington Road between 8 AM – 5 PM Monday – Friday for utility and roadway work. 

WellingtonRoad at Prince William Street will have daily lane closures from Monday,Oct. 29 through Friday, Nov. 2. Through traffic will be able totravel along Wellington Road, but turns may be restricted. 

The aboveground temporary water line (yellow pipe) will be removed within the next twoweeks.  

Our Public Works team met with the community at City Hall to discuss the Prince William Street project.  Staff presented information on the project and solicited feedback.  Links to this information are shared below.  All documents are in PDF format.

Project Status:  

  • Underground Electric, Comcast and Verizon – completed
  • Columbia Gas work – completed
  • Advertised for construction – December 12, 2017
  • Bids received – February 9, 2018
  • Award Project – June 2018
  • Begin Construction – July 2018
  • Contractor - Fort Myer Construction and Utility Services Company
  • Project Complete – Fall 2019